The month of July continued work to install the first floor HVAC and plumbing. The month will also bring additional work to install the foundations and build the ground floor walls for the remaining areas and begin the placement of the structural steel.
In addition to the weekly construction updates posted to the website (on the right-hand side of this page), interested members of the public now can view progress on the construction site in real time with a
live video stream of the project.
NOTE:
If you have any concerns or questions during the duration of the project, please contact Dan Kiefer, project manager with Massaro CM Services, LLC, at [email protected] or 412-670-0981.