logo
School Construction update: October 2017
The month of October continues work to install the trusses on Scott Primary and install the CMU blocks for the gym and cafeteria areas, and pour the concrete slab. October will begin work to form the new entrances on Scott Avenue. 


In addition to the weekly construction updates posted to the website (on the right-hand side of this page), interested members of the public now can view progress on the construction site in real time with a live video stream of the project.

NOTE:

If you have any concerns or questions during the duration of the project, please contact Dan Kiefer, project manager with Massaro CM Services, LLC, at [email protected] or 412-670-0981.
1800 Mt. Royal Boulevard     Glenshaw, PA. 15116     P 412-492-1200     F 412-492-1236
1800 Mt. Royal Boulevard Glenshaw, PA. 15116 P 412-492-1200 F 412-492-1236
© 2016. Shaler Area School District. All Rights Reserved - School CMS created by eSchoolView
View text-based website